Company B offered several opportunities for creative
application of MPS and BOM techniques. The company's product
structures are complex with many levels and subassembly
arrangements. In developing a scheduling for Company B, one must
first recognize that this is really several companies within a
company. Many have argued that this is not true. Their position
was that there are several end products for which all components
must come together into a final assembly. To separate the
structure and create separate schedules would compromise the
company's ability met customer demand. Further, opponents felt
that attempts to master schedule below the end item level would be
confusing due to the added manual intervention of maintaining
multiple master schedules. Indeed, master scheduling below the end
item does require additional manual intervention and control, but
as will be demonstrated, is well worth the effort.
Scheduling Company B
The first concept to understand is that Company
B is indeed "several companies within acompany"; for
scheduling purposes. Company B looks like most other companies
with large, complex structures. It has many parts and
subassemblies coming together at a configuration of "demand
rated" tooling for final assembly. The final assembly process
has several positions that move at the same rate; that being the
demand rate of the customer. The fallacy in the thinking was that
all previous and supporting operations of final assembly had to
move at the same rate as final assembly. While it is true that all
operations must move at least as fast as final assembly, it
is not true that they have to move as fast as final assembly.
The mindset that all operations need to be
paced at the same rate as the end of the line causes a company to
add cost to its products. This added cost is a product of the
schedule failure that is being built into the schedule before it
ever goes to the floor. A good example of this condition is
revealed by looking at a typical product; the GSIV.
GSIV's demand rate was for one finished product
every five (5) working days. Therefore, all supporting assembly
operations were presented with a schedule for one each of their
subassemblies every five working days. In turn, the Industrial
Engineering Department set the manning levels for the subassembly
departments based upon the schedule requirements. The lE's were
careful to match the manning levels (capacity) very closely to the
load so as to maximize direct labor efficiency. While this
approach sounds good in theory, it is poor in practical
application. By balancing capacity (workers) to the schedule the
company is setting itself up for a fall the first time one of the
areas misses schedule. Since capacity=schedule, there is very
little, if any, residual capacity to regain schedule when (not if)
an area falls behind.
Conversely to falling behind, some subassembly
areas will get ahead of schedule. This condition creates another
set of problems equally as bad as missing schedule. Since the
workers are dedicated to the GSIV product line, in particular,
certain assemblies, they have nothing to do except build ahead.
This creates a rippling affect through the rest of the
organization. Order Release is requested to release more work.
Material Planning must replan material to respond to the
accelerated schedule, and Purchasing must expedite material from
suppliers. All of these needless activities add cost to the
product, but they do so in an indirect fashion, contributing
mostly to overhead. These costs are not readily visible when the
cry goes out for more work. The only visible impact at the time is
the fateful "direct labor efficiency" measurement. There
is a way to avoid the pitfalls mentioned above, that being through
proper MPS and BOM techniques, and a recognition on the part of
management that there are other ways of running a business.
Since the rate tooling moves the same at every
position, we can master schedule at as many of those positions as
we choose. The way in which we select the positions to be
submitted to MPS is based upon the subassemblies that feed a given
position. For example, the position that drives the bonded
assembly requirements can be selected to provide scheduling
flexibility for the bonding department. The positions that drive
certain types of minor subassemblies can be master scheduled for
better control of those areas. Since these subassemblies are now
master scheduled, they can have rates of move developed
individually. The only constraint we have to keep in mind is
that the rate of move cannot be slower than the final assembly
positions. The advantage
of altering the schedule for the subassemblies
is that we can better manage the labor, most likely reduce it.
The previous schedule for a subassembly area
would have had all of the supporting subassemblies moving at one
every five days. Now we can change the rate of move on certain
subassemblies to perhaps two days; maybe three for others; or
four. Instead of certain workers being assigned to certain
subassemblies, they are now assigned to a family of subassemblies.
Since we can vary the schedule rates on the subassemblies we can
be more flexible with the workers. Now the workers can be mixed
and matched to a variable number of subassemblies. This
arrangement provides other benefits. Once the proper mix of
subassemblies and rates are identified, bills of material are
constructed under them to allow MRP to process and schedule the
components and raw materials. Now the components and raw materials
match the schedule and can support the flexibility required in
subassembly.
By using the methods described, Company B can build flexibility
into its system rather than schedule failure.
To be Continued
STAY
CONNECTED
To
stay current on bullet-proofed manufacturing solutions, subscribe to
our free
ezine, "The Business Basics and Best Practices Bulletin."
Simply fill in the below form and click on the subscribe button.
We'll
also send you our free
Special Report, "Five Change
Initiatives for Personal and Company Success."
Your
personal information will never
be disclosed to any third party.
Manufacturing
leaders have a responsibility to educate and train their team
members. Help for developing a self-directed, World Class
Manufacturing training program for your people is just a click
away:
http://bbasicsllc.com/training-modules.htm
You
are welcomed to print and share this bulletin with your
manufacturing teams, peers, suppliers and upper management ...
better yet, have them signup for their own copy at:
http://bbasicsllc.com/subscribe.htm
With
the escalating spam-wars, it's also a good idea to WHITELIST
our bulletin mailing domain via your filtering software or
control panel:
bizbasics@getresponse.com
This will help guarantee that your bulletin is never deleted
unexpectedly.
Manufacturing
Knowledge you’ll not find at offsite
seminars nor in the books at Amazon.com
Lean Manufacturing - Balanced Scorecard
ISO 9000:2000 - Strategic Planning - Supply Chain
Management - MRP Vs Lean Exercises - Kaizen Blitz
Lean Six Sigma - Value Stream Mapping
All at one Website: Good
Manufacturing Practices
Lean
Six Sigma Training Thinking
Out of the Box
Balanced
Scorecards Strategic
Tactical Planning
Supply Chain Inventory Management Total
Quality Management Principles
Lean
Manufacturing Implementation Lean
Manufacturing Principles
Email: Click
here Privacy Policy
|