Let's look first at what is often called the
"disconnected flow" environment. (Also known as
"batch" or "job shop".) This environment is
characterized by operation times (set-up and run) that are in the
order of 20% of the total throughput time, with the remaining 80%
being in wait, move, transit and queue time.
In this environment, production typically
involves several individual operations, movement of material
between operations is non-linear, and relatively long set-up times
are the norm. Capacity Requirements Planning (CRP) involves
breaking production orders down into their individual operations
and calculating the capacity required for each operation from
routing data. The timing of the capacity requirements are
determined by scheduling backward from the order due date
(Figure 2). The capacity requirements are then collected for
each individual work center and can be displayed in a time-phased
fashion as in Figure 3. Since in the typical manufacturing plant
there are likely to be hundreds of orders scheduled to move
through a given work center in a week, this report is likely to be
very lengthy. The report shown in Figure 4 shows the same
information in summarized form.
Note that the summary report (Figure 4) shows
periods of both overload and underload on both the equipment and
the work force. It is obvious that one or more of the above noted
changes must be employed to bring this situation into balance.
There are two ways to go about this—finite scheduling and
capacity planning. The former technique is based upon the concept
of automatically scheduling work within a stated resource
capacity. The latter technique is based upon the "infinite
load" concept of initially scheduling work regardless of
resource capacity and then selecting the most appropriate solution
via human analysis and decision.
The debate between these two techniques rages
from time to time. Let it be said that neither is perfect. The
problem with infinite loading is merely that capacity is not
infinite, and to arrange a schedule based solely on this technique
will most certainly lead to trouble due to both overloaded and
under-loaded resources. On the other hand, the finite scheduling
technique assumes that the available capacity cannot be changed
and immediately leaps to the "reschedule" solution,
which in turns violates the validity of the overall plant
schedules since lower level schedules have been altered without
reconciling them back to MRP and the Master Schedule.
What is useful is a combination of the two
techniques. In the very short term, adjustments to available
capacity are at best costly (i.e. overtime) if not altogether
impossible (i.e. additional equipment). Thus, finite scheduling
is reasonable in this part of the scheduling horizon. On the other
hand, adjustments to available capacity are quite practical in the
mid to long term. Utilizing infinite loading techniques in these
areas can be very effective provided the human participation
element in the capacity planning process is properly employed.
Use of finite loading in the mid to long term
violates one of the objectives of capacity planning identified
above: to solve capacity problems in a timely manner to meet
customer needs. Presumably, the projected overloads and
underloads are dictated by changes in the expected specifications,
mix, or the volume of business. Looking again at Figure 4, the
planned orders that are causing the overloads in the future would
be scheduled out by the finite scheduling process, thus rendering
it impossible to meet the Master Schedule that drove the material
requirements that in turn created the capacity requirements. On
the other hand, using Capacity Requirements Planning to address
this situation would likely result in action to increase the
available capacity in the appropriate future time frame so that
the overload condition will be resolved by the time the planned
work is released for actual production. This would minimize—if
not eliminate altogether— the need for finite scheduling in that
particular period.
Rough-Cut Capacity Planning (RCCP) is a
simplification of the CRP process utilizing a "resource
profile" for a product rather than a detailed routing for
every individual part. Because of limitations of the process such
as lack of inventory netting, lead time offsetting, and lot size
and set-up assumptions, RCCP should only be used to estimate
capacity requirements for the mid to long term. Not to be
interpreted as a substitute for CRP, RCCP should be used as a
process for validating the aggregate Production Plan or the Master
Schedule prior to releasing those plans for full MRP and CRP
calculations.
Input/Output Control (I/O) is a process of monitoring the flow
of work to and from each work center against what was planned, and
is an excellent tool for controlling the amount of queue in a work
center.
To be Continued
STAY
CONNECTED
To
stay current on bullet-proofed manufacturing solutions, subscribe to
our free
ezine, "The Business Basics and Best Practices Bulletin."
Simply fill in the below form and click on the subscribe button.
We'll
also send you our free
Special Report, "Five Change
Initiatives for Personal and Company Success."
Your
personal information will never
be disclosed to any third party.
Manufacturing
leaders have a responsibility to educate and train their team
members. Help for developing a self-directed, World Class
Manufacturing training program for your people is just a click
away:
http://bbasicsllc.com/training-modules.htm
You
are welcomed to print and share this bulletin with your
manufacturing teams, peers, suppliers and upper management ...
better yet, have them signup for their own copy at:
http://bbasicsllc.com/subscribe.htm
With
the escalating spam-wars, it's also a good idea to WHITELIST
our bulletin mailing domain via your filtering software or
control panel:
bizbasics@getresponse.com
This will help guarantee that your bulletin is never deleted
unexpectedly.
Manufacturing
Knowledge you’ll not find at offsite
seminars nor in the books at Amazon.com
Lean Manufacturing - Balanced Scorecard
ISO 9000:2000 - Strategic Planning - Supply Chain
Management - MRP Vs Lean Exercises - Kaizen Blitz
Lean Six Sigma - Value Stream Mapping
All at one Website: Good
Manufacturing Practices
Lean
Six Sigma Training Thinking
Out of the Box
Balanced
Scorecards Strategic
Tactical Planning
Supply Chain Inventory Management Total
Quality Management Principles
Lean
Manufacturing Implementation Lean
Manufacturing Principles
Email: Click
here Privacy Policy
|