PRODUCT DESIGN FOR REPETITIVE
Traditional product
design approaches emphasize common components, modules, and
subassemblies, which are made in large quantities and placed into
stock to be ready to be used in different higher-level assemblies.
In contrast, designing products for repetitive manufacturing focuses
on moving the initial raw materials nonstop through the entire
manufacturing process until they have been completely transformed
into the final finished goods. JIT, flow, or repetitive environments
utilize a flattened bill of materials (BOM) structure in planning
and inventory accounting. Flattening BOM eliminates moving
semifinished materials in and out of stockrooms, thereby reducing
handling, paperwork, and lead times.
1 No manufacturing
involvement in product design. 10+ level BOM, paper drawings in
drawers in Engineering, so old they crumble when touched.
2 A little
manufacturing involvement in product design. Products designed to be
built in stages, with semifinished inventory storage at each stage.
6+ level BOM, bills of materials are computerized and can be
accessed by authorized
employees.
3 Some manufacturing involvement in product design, to start
minimizing intermediate levels. 4+ level BOM, starting to convert
MRP-oriented, multilevel BOMs by flattening them to reflect how
parts are manufactured, or by changing intermediate levels to
"phantoms."
4 Extensive
manufacturing involvement in product design to minimize BOM levels.
Two or three-level BOM, regular audits of billof material accuracy,
change procedures are in place and being used. BOMs may contain
"phantoms."
5 Manufacturing and
suppliers heavily involved in design, design to support flow not
work orders, options and features added at the very end. One-level
BOM; completely accurate, updated constantly, on computer, and
available on manufacturing floor. BOMs may contain "phantoms."
ROUTINGS—PAY POINTS
Routings contain
operation instructions, which tell the operator how to
perform the specific step of the manufacturing process, and -which
are essential for job shop/discrete plants. They should be replaced
by cell or assembly line methodologies in a repetitive operation,
and the number of operation steps should be minimal. There should
be only one pay point (at the end), unless a high-value serial
number component needs to be tracked in the middle of the operation.
Pay points are used for backflushing.
1 6+ operation
steps/routing; no pay points
2 4+ operation steps/routing; no pay points
3 3+ operation steps/routing; 3+ pay points
4 2 operation steps/routing; 2 pay points
5 1 operation step/routing; 1 pay point
SCHEDULE ATTAINMENT
While meeting
schedules is important for discrete manufacturers, for repetitive
manufacturers it is absolutely essential, because repetitive links
operations and eliminates inventory. Thus, if one cell or work area
fails to meet its schedule, downstream work areas might run out of
work, and a customer shipment will probably be late.
1 90 percent
on-time completion of work at all work cells, measured by shift.
2 95 percent on-time completion of work at all work cells, measured
by shift.
3 98 percent on-time completion of work at all work cells, measured
by shift.
4 95 percent on-time completion of work at all work cells, measured
hourly.
5 98 percent on-time completion of work at all work cells, measured
hourly.
To Be Continued