PLAN THE PROJECT
This step
transforms the project definition into a plan that can be
controlled by the project manager. The first activity in this step
is to identify the work that must be done to accomplish each of the
objectives and who is responsible for getting it done. Don't forget
the activities of presenting information and making decisions. They
typically take longer than planned because few organizations make
decisions on the spot. The level of detail in the definition of the
work to be done will vary by project and by the timing of the work.
There should be a minimum of three to five activities leading to
each deliverable. The near-term activities covering the first 25 to
30 percent of the schedule should be defined as precisely as is
practical. The later activities can be refined as the project
progresses and more information becomes available.
Once the work to be
done has been identified, the duration of each activity must be
estimated and the relationships among the activities must be
defined. There has been a great deal of debate about whether
duration, effort, or both should be estimated. The duration seems to
be most critical in projects producing "soft" results and depending
on part-time resources. It may be necessary to include estimates of
effort for a few critical resources. It is important to include
explicit management reserves in the plan so that the project manager
can decide when to use that time. If the individual estimates are
inflated to include a reserve, the activities will consume the time.
This rough project
plan provides the first opportunity for testing the feasibility of
the target dates and deliverables. The testing is similar to
rough-cut capacity planning in that only critical resources and
blocks of time are considered. If the project is not feasible, a
combination of three types of project modification must be agreed
upon:
• Resources can be
added.
• The scope of work can be reduced.
• The target date can be changed.
This is why the
objectives that were not necessary and the deliverables that were
not critical were identified in the define-the-project step. They
can be dropped from the plan or rescheduled beyond the original
target date. This is recovery planning in the earliest stages of the
project.
Once that it is
determined that the work to be done is feasible in the time allotted
with the available resources, a real project plan must be developed.
The project network is the basis for all project controls. Gantt
charts are fine for reporting upward and outward and for
representing the project schedule. However, a project cannot be
controlled unless the relationships among the activities are
understood. The project network must realistically represent these
relationships.
It is tempting to
combine the project network and schedule into a single diagram. This
may have been necessary for manual project planning and control,
but should be avoided to keep the level of effort for maintaining
the project network reasonable. At this point, pure finish-to-start
and start-to-start relationships should be used unless there is
solid information on the degree of overlap. This somewhat
overstates the duration, but this time can be used to recover from
deviations from the plan. The completed project plan provides the
second test of feasibility of the project. If the network indicates
that targets can't be met, the previously defined alternatives must
be evaluated.
There are many
microcomputer-based project management systems that can assist in
developing the network and maintaining the plan. They are also
powerful enough to allow the project team to make
professional-looking presentations on projects that are not
understood or being controlled. Use these tools wisely to reduce the
amount of routine work, but don't expect them to control the
effort.
To Be Continued
For balance of this article, click on the below link:
Lean Manufacturing Articles and go to Series 01