Calculating the Number of KANBANs
A supplier-customer relationship typically requires a certain
amount of stock to buffer each from the other's lack of regularity.
In a totally regulated shop, no stock is needed, and no KANBANs are
needed either. Demand is either perfectly level, or production
flexibility is infinite: that is total Just-In-Time, and it does not
exist anywhere. Like Total Quality, it is a journey. So while we do
have stock, and we do want to manage it using KANBANs, this stock
must be justified by KANBANs (Rules 3 and 4 order all inventory to
be justified by a KANBAN). Each standard quantity of stock is
assigned a KANBAN. How many KANBAN cards should be authorized? That
is the question. How many KANBAN cards are needed to obtain an
ideal in-process investment configuration which respects
inter-operation imbalances and which protects an adequate level of
operational efficiency? More cards in the customer-supplier feedback
loop = more stock, more protection, more costs, more lead time,
etc.
Several formulas have been proposed to calculate the number of
KANBANs required in a KANBAN loop. They all suffer from the same
weakness: they consider each KANBAN loop individually, forgetting
that efficiency and work in process (WIP) are rather a function of
total mix and customer-supplier imbalances. This faulty reasoning is
typical of most computerized approaches, even of MRP II systems,
which ignore or simply report global impacts but rarely use them as
a fine-tuning input.
For example, most of the formulas ignore setup times, which, any
shop foreman will confirm, are, or should be, the most important
factor determining lot sizing in a context of relatively fixed
(short term) capacity. Resulting lot sizes force de-synchronized
operations and flows that largely exceed unit demand by period,
resulting in low stock turnover rates, inflexibility and long lead
times.
If the KANBAN is to be a flow management technique, it must
integrate these conflicts routinely. It must also integrate issues
relating setup times to the volumes that must be produced and the
current capacity constraints. We will borrow from the economic order
quantity (EOQ) logic the notion of finding an optimum stocking
configuration balancing setups with the cost of inventory. We will
also use the planning tools available in MRP to establish the mix
and forecast demand and capacity constraints.
The approach we propose to calculating KANBAN loops also borrows
concepts from the LIMIT technique described by Haety, Plossl and
Wight and documented by Fogarty & Hoffman (Ref. 3, p. 298). The
purpose of this technique is to revise individual lot sizes when the
lot sizing of all the parts needing to be produced exceeds available
capacity. This is done using formulas which adjust lots sizes in
inverse proportion to the excess loading. The interesting aspect of
this approach is really the idea of fine tuning individual lot sizes
based on the global situation. The LIMIT technique has been used
specifically to correct the cumulative effect of theoretical EOQs
when the total capacity is insufficient to produce the lot sizes
calculated.
We will use this approach, not to correct bad EOQs, but to directly
determine lot sizes to adequately reflect the general shop
constraints as a dynamic function of actual loading. These optimized
lot sizes will then become important factors in establishing and
managing the KANBAN. One major disadvantage of traditional EOQs is
its well-known inability to adapt itself to the moving sets of
constraints and opportunities being raised on the shop floor every
day. The 7th rule eliminates this problem.
To validate that the KANBAN implementation proposed is acceptable
from a managerial perspective, we will validate its results against
stock turnover objectives as these are usually an important
performance measure used to evaluate the Materials or Production
functions.
A Few Basic Concepts
In the following sections, we will implement the KANBAN step by
step. Keep the following concepts in mind as we implement an
integrated solution using KANBANs.
• The shop is only as fast as its slowest mover, its bottleneck. It
is wasteful to produce more on the other work centers. Spinning
wheels uselessly only creates more in-process stocks and stretches
manufacturing lead time. If plant throughput is insufficient,
increase the capacity of the bottleneck first. Bottleneck
conditions may move from one work center to another based on
fluctuations in the mix.• Maximize the utilization of the bottleneck work center, of course.
• In the very short term horizon, the one relevant for the use of
KANBANs, equipment and labor capacity are a fixed cost, and are
therefore not considered a variable cost.
• Maximizing their
utilization to create inventory (to appear efficient) only consumes
raw materials too early, producing stock for which there is no
immediate customer. See the second rule of KANBAN.
To implement the 7th rule, we must assess shop loading to identify
work center constraints (bottlenecks) and opportunities, and, as a
result, to determine feasible turnover rates. Then, we will
determine guidelines to set optimum lot sizes. We will determine the
size of the KANBAN loops for each item produced. Finally, we will
consider the KANBAN implementation and management process. The next
11 points and accompanying notes cover these issues.
To Be Continued
For balance of this article, click on the below link:
Lean Manufacturing Articles and go to Series 01