|
|
In the Manufacturing world, building the correct amount of the
needed product at the appropriate time separates a very successful
company from the rest of the pack. Many companies have assembly
lines or machines that can churn out product at a high rate of
speed—only to find that requirements have changed, and the changes
were not communicated. At a time when customer service is of
paramount importance, a competitive company must be highly
responsive to customer needs (i.e., flexible). A good shop floor
control system can be the competitive edge that a manufacturing
company needs to be competitive.
This paper will define shop floor control and give some case study
examples of shop floor control in a traditional manufacturing
environment as well as the necessity of shop floor control in a
dynamic JIT environment. We will also look at shop floor control
from the perspective of both management and the production floor.
Shop floor control is defined as a system for utilizing data from
the shop floor to maintain and communicate status information on
orders and at work centers. In practice, a working definition is an
individual on the shop floor, a supervisor, lead person or team
leader, using the system data base and communicating the status of
work to the scheduling individual, a master schedule planner or
manager. The status of work is compared to the capacity of the work
center, which then becomes a question of balance and priority. While
this is certainly a simplified definition of shop floor control, the
basics remain clear: if a manufacturing plant has 100 hours of
capacity and 500 hours of work, the chances are pretty good that the
work is not going to be completed. A good shop floor control system
will communicate this information before it is too late.
Getting Started—Issuing Work to the Floor
The first step in controlling the shop floor is actually getting
work to the floor. Whether your company is issuing jobs via a work
order packet or has a CRT on the floor flashing the next priority,
the two ingredients of successful shop floor control are
these—material and capacity. Without sufficient material or
capacity, there is no MRPII or ERP system on the planet that will be
of much help meeting current due dates. There are some very basic
rules that have been around since Henry Ford began rolling model T's
off his assembly line that certainly warrant repeating.
Work should not be issued to the floor if all of the material is not
available. This may be manufacturing's most violated rule. There is
the rationale in manufacturing that it is better (i.e., more
efficient) to put work on the floor with material shortages, batch
in tote pans at a subassembly level, and then put all available
labor on the job when the shorted material arrives. While this
technique may have gotten a few facilities out of a jam, it is
definitely not the recommended method of operation. There are risks
associated with this practice that will sooner or later negatively
impact the process. The risks could be a quality issue where a
defect is being built into the batched subassemblies that would be
caught at final test—only when final test is started, there are
several days of subassemblies that may need to be reworked. A
customer requested revision change would have the same adverse
affect. The customer could also change priorities, leaving
manufacturing with the dilemma of either holding tote pans full of
subassemblies that are not at a reportable level or having to
finish the build, using valuable resources. The resources could be
capacity or material that could better be utilized to provide the
customer with the product being requested.
The second most violated rule may be issuing work to the shop floor
without adequate capacity. While MRPII systems assume that capacity
is infinite, this is not actually the case. There are methods of
increasing capacity (overtime, increasing the work force,
consignment) that require some flexibility, but are still finite.
This means that work must be released to the shop floor in
quantities consistent with the capacity of the shop floor. It is
important that the due date be realistic. Nothing is as frustrating
or demoralizing to a supervisor or team leader than receiving work
with a due date that is unattainable or even past due. There is not
a good reason to release past due orders. Orders released that are
over capacity or with unrealistic due dates make the schedulers and
productions job even more challenging (i.e., difficult). For
example, in Figure 1, work center 200500 has a daily capacity of 200
units. Today's date is February 1st. This is the schedule for work
center 200500. From looking at this schedule, which job is needed
the most? All things being equal, the listed order is probably the
correct order, but this example certainly begs for questioning. Do
we really need jobs 001 and 002? Has the customer been calling and
asking for these jobs? Are these actual due dates or perceived due
dates? Is there a fudge factor attached to the due dates because
past history indicated due dates had no real meaning at the XYZ
Company? There are questions that should be addressed and it's
important that scheduling and the shop floor communicate with each
other.
To be Continued
STAY
CONNECTED
To
stay current on manufacturing
competitive knowledge,
please subscribe to our weekly bulletin, "Manufacturing. Basics
and Best Practices (MBBP)." Simply
fill in the below form and click on the " subscribe
button."
We'll
also send you our Special Report, "6-Change Initiatives for
Personal and Company Success."
All at
no cost of course.
Your
personal information will never
be disclosed to any third party.
privacy policy
Here's
what one of our subscribers said about the MBBP Bulletin:
"Great
articles. Thanks for the insights. I often share portions of your
articles with my staff and they too enjoy them and fine aspects
where they can integrate points into their individual areas of
responsibilities. Thanks again."
Kerry B. Stephenson. President. KALCO Lighting, LLC
Lean Manufacturing Menu
Lean
Manufacturing Improvement
Performance
Management Improvement
ISO 9000:2000
Improvement
Continuous
Process Improvement
Value Steam
Mapping Improvement
Strategic
Planning Improvement
Supply
Chain Management Improvement
"Back
to Basics" Training for anyone ... anywhere ... anytime
Business
Basics, LLC
6003 Dassia Way, Oceanside, CA 92056
West Coast: 760-945-5596
© 2001-2007 Business Basics, LLC
|